Hello!

Starting Monday v.49, AFRY will carry out a ventilation check, where they will check drawings and make an air measurement in all spaces.

This is done when we want to update these because several different changes have been made to the house over a longer period of time.

This means that they need access to your premises.

You don't need to think about anything special before the work, but more that they will have to lift the roof tiles.

The work does not involve any disturbing noise such as drilling / sawing.

The work is carried out during the day 7-16 and is planned to be finished no later than 20/12-24.

AFRY will start work on Ulls Väg 29a in the northern part of the building and work downwards towards Ulls Väg 29c.