Details
Ångströmlaboratoriet Hus 5 (C01090015)
Project Octopus, Disturbing work in House 5
In the Octopus project, we would like to carry out work in House 5 that involves drilling into walls during the Christmas and New Year period.
The drilling is a preparation for our upcoming work according to the information we have sent previously.
We want to work on all levels of the house and on exterior walls where we need to install a new cable duct for our new cables and it needs to be attached to the wall with screws.
The sound will propagate in the building and will continue for periods during the following days.
- December: 22nd, 23rd, 29th and 30th
- January: 2nd and 5th
Please let me know if this work doesn't work for you.