Information letter week 39-40 2025

Details

Utemiljö (B0011000)

The Pussen project

Week 39

Assembly of steel details for bridges and wooden decks and construction of decking on wooden decks and bridges. Laying of slabs and friezes. Casting of pillar shafts for barbecue huts.

Week 40

Continued construction of decking on wooden decks and bridges. Installation of barbecue huts, adjustment for grass areas, laying of tiles and planting of perennials.

Preparatory work of the Pavilion

In connection with preparatory work for the upcoming construction of the Pussen pavilion, ground work will begin at the end of week 38/beginning of week 39. The work will involve some disruption in the area. The parking lot, which is marked on the map below, will be cordoned off with construction fencing to create a work area. The cordoning off will take place in the middle/end of week 38 and will apply throughout the construction period. The lighting in the parking lot has already been taken down. Four lighting posts have been removed and only one post at the beginning of the parking lot is in operation. This means that the parking lot will be unlit until it is cordoned off. The first works include preparatory ground work for water, electricity and fiber. This will be followed by work to lift there and establish the new Pussen pavilion.