A-huset (B0011011)
House A
Renovation of all toilets in Alfhuset will begin on April 7 and continue until June 5. The work will start on the top floor (A500) and then continue downwards. Each floor will be completed before work continues on the next. The estimated time required is approximately three weeks per floor, which corresponds to a total of approximately nine weeks.
In the A1000 corridor and in the culvert between building A and building B, replacement of fixtures is underway. Door replacement is underway between Kideus and the 98 section (A1500 corridor).