The roof work to update the roof safety and repair damage to future-proof the lifespan is still ongoing. This week, sheet metal work in stage 1 was completed. Work is underway to move the guardrails and materials to the next stage and continue there.
The schedule has been slightly delayed compared to before as we have had problems with both illnesses and deliveries, but the end time is expected to remain according to the original schedule. See attached for the updated schedule.
While the sheet metal is being replaced, this will cause noise that affects and disrupts operations. These sounds, as the sheet metal worker shapes the sheet metal with a knocking sound, continue throughout the working days between 7am and 4pm.
We hope you will be considerate of this.