Status update courtyard B3

Details

Humanisthuset (J0008009)

The work is going according to schedule and next week the foundation and excavation work will be completed. Until the holidays, curbs, slate, furniture and grass will be installed. When cutting stones and compacting soil, disturbing noise may occur. After the holidays, work with planting shrubs will continue before we inspect at the end of August. The mailing includes a schedule and work materials for the courtyard. The final design may differ from the produced work materials. If you have any questions, please contact project manager Björn Alenius. Bjorn.Alenius@Akademiskahus.se