SLU, Sveriges lantbruksuniversitet (J0027001)
The work is going according to schedule. Next week we will lift the new ventilation unit through the roof and will then use a mobile crane. The crane will temporarily stand outside the beech forest but is not expected to disrupt accessibility or operations. Inside, walls are being completed, painting is underway, and installations that will be located above the suspended ceiling are being installed. Currently, the contract will be inspected at the end of October, after which the interior and various technologies will be installed.