Friday 31 October, 2025
Information letter week 45-46 2025
Campus safety walk completedA safety walk was held on campus on September 25. Participants in the walk were Akademiska Hus, LTU, representatives from the unions at LTU, Luleå Municipality, Rikshem, Studentbostäder and Teknikens Hus.The purpose of the walk was to ensure a safe campus by identifying areas that need action on and adjacent to the campus. Examples of areas identified include: areas with increased lighting needs, areas in need of clearing undergrowth, areas with poor visibility/risk of accidents, poor accessibility due to bicycles, areas in need of upgrading, road safety, and information needs.The issues that arose during the hike have been partially addressed and will be worked on in the coming time.
Friday 31 October, 2025
Information letter week 45-46 2025
The Pussen projectWeek 45A few additions are being made, including wooden decking and sheet metal for windbreaks.Week 45 and 46The remaining lighting poles, which have been delayed by the supplier, will be installed and put into operation during week 45.Final inspection will be carried out at the end of week 46. The barriers around the work area will remain in place until the final inspection is approved.
Friday 31 October, 2025
Information letter week 45-46 2025
The Pussen projectWeek 45A few additions are being made, including wooden decking and sheet metal for windbreaks.Week 45 and 46The remaining lighting poles, which have been delayed by the supplier, will be installed and put into operation during week 45.Final inspection will be carried out at the end of week 46. The barriers around the work area will remain in place until the final inspection is approved.
Friday 31 October, 2025
Information letter week 45-46 2025
House ELighting replacement in classrooms and in corridor E230.
Friday 31 October, 2025
Information letter week 45-46 2025
House CDamage has occurred to one of the walls at the light garden. Repairs will be made shortly.The lighting replacement in the light yard is taking a break and the work will continue in week 51.
Friday 31 October, 2025
Information letter week 45-46 2025
ALFA HouseFrom week 45 onwards, construction work will be carried out in offices A281, A282 and A269.
Friday 31 October, 2025
Information letter week 45-46 2025
House AInstallation of solar cells is underway at Building A. We have paused all exterior work during the exam period weeks 43-44.Next week, November 5-7, we will begin taking down the safety barrier and the stair tower so that a crane/crane truck can be used to and from these days, and a crane truck may also come and pick up counterweights during week 46.Otherwise, mainly interior work is underway in technical areas.
Friday 31 October, 2025
Information letter week 45-46 2025
Outdoor environmentThe lighting replacement is still ongoing in the courtyards at Building E and in Building A.Leaf removal from gutters and roofs is carried out on all houses.
Friday 31 October, 2025
Information letter week 45-46 2025
Outdoor environmentThe lighting replacement is still underway in the courtyards at Building E and in Building A. Leaf removal in gutters and on roofs is being carried out on all buildings.House AInstallation of solar cells is underway at Building A. We have paused all exterior work during the exam period weeks 43-44.Next week, November 5-7, we will begin taking down the roof safety and the stair tower so that a crane/crane truck can be present to and from these days, possibly a crane truck will also come and pick up counterweights during week 46.Otherwise, mainly interior work is underway in technical areas.ALFA HouseFrom week 45 onwards, construction work will be carried out in offices A281, A282 and A269.House CDamage has occurred to one of the walls at the light garden. Repairs will be made shortly.The lighting replacement in the light yard is taking a break and the work will continue in week 51.House ELighting replacement in classrooms and in corridor E230 The Pussen projectWeek 45A few additions are being made, including wooden decking and sheet metal for windbreaks.Week 45 and 46The remaining lighting poles, which have been delayed by the supplier, will be installed and put into operation during week 45.Final inspection will be carried out at the end of week 46. The barriers around the work area will remain in place until the final inspection is approved.Campus safety walk completedA safety walk was held on campus on September 25. Participants in the walk were Akademiska Hus, LTU, representatives from the unions at LTU, Luleå Municipality, Rikshem, Studentbostäder and Teknikens Hus.The purpose of the walk was to ensure a safe campus by identifying areas that need action on and adjacent to the campus. Examples of areas identified include: areas with increased lighting needs, areas in need of clearing undergrowth, areas with poor visibility/risk of accidents, poor accessibility due to bicycles, areas in need of upgrading, road safety, and information needs.The issues that arose during the hike have been partially addressed and will be worked on in the coming time.
Thursday 23 October, 2025
Preparatory work Pussen Pavilion
Adapteo and NCC will place the crane inside the work area that they have fenced in. See updated APD plan.